Pex.2025.11.2.13
Updated
by Frank Pedersen Moe
Price adjustment wizard
Simplifying the adjustment of sales hour prices for projects with the use of price indexes.
First step is to create the indexes to be used on the projects: Cepheo® > Project control > Setup > Price index

Then specify the index to be used on the project and an adjustment date, you can also mark it to be handled manually.

Go trough all projects that is to be managed and update these values
Then start the price wizard: Cepheo® > Project control > Periodic > Price adjustment wizard
Step 1. select an adjustment date

Step 2. Review the changes, here you can also make your own adjustments

Step 3. Apply the changes

There is also a parameter setup that needs to be configured: Cepheo® > Project control > Setup > Project control parameters

Here you can specify criteria for project group, rounding ++. Also all changes are logged