Automatic reporting as finished for sub-productions
Concept
The concept of automatic reporting as finished for sub/reference productions, is introduced to support sceneries of continuous production for multiple production/batch orders combined in a hierarchy…
Prerequisites and setup
The BOM/formula line marked for 'Automatic reporting as finished', must be setup for automatic reporting as finished, and the flushing principle must be set to "Finish". Both Co-products as well as r…
Reporting quantity as finished from finished product
When 'Reporting quantity as finished' for a FP production, using the automatic BOM consumption principle and posting, the consumption of next level product (Bulk) will automatically report the wanted…
Mix pools
Before firming planned production/batch orders, the planned orders can be combined into a new mix pool. Mix pools can also be created by using the mixing principle for formula versions. The Mix pool…
Automatic reporting as finished for sub-productions
Automatic reporting as finished for sub-productions. Assigning a Mix pool to planned orders or batch/production orders, can also be used in combination with the consolidated batch order framework to…
Respect physical conditions during automatic reporting as finished
Summary. The Automatic reporting as finished for sub-productions functionality has been enhanced to support production scenarios in which bulk production or batch orders must be started according to…
Ending productions from finished product production
If less quantity than planned of the FP is 'Reported as finished' it is assumed that less quantity of the BP/CP will be consumed as well. The quantity for BP/CP is automatically corrected for the las…
Reporting negative quantity as finished from finished product (roll-back)
If a negative quantity of the FP is 'Reported as finished', the automatic 'Reporting as finished' for the BP will also be performed with a corresponding negative quantity. If the FP is setup to use w…
Reporting overproduced quantity as finished from finished product
If a larger quantity than planned of the FP is reported as finished, this means that more of the BP must be consumed as well. If there is not enough of the BP planned in the mix pool, the quantity fo…
Supported process flow
Automatic route consumption
An enhancement has been introduced to the Automatic reporting as finished for sub-productions feature. In the previous solution, the A utomatic Root Consumption parameter was always set to Route grou…